University of Utah Hospital Infill Project Update

We always knew that the UUH Infill project would be a challenging construction process. I’ve personally compared it to building a ship in a bottle, because nearly every building component and piece of equipment must be brought over the top of the hospital and lowered in by a crane. The building is surrounded on all 4 sides and all of the utilities and power only have one way into the building.

Though the project is halfway done, we’ve only constructed the first floor. The next 6 months will see completion of the remaining 4 floors and all of the finishes. The excavation and demolition have proven difficult, taking 1 ½ floors of dirt out by crane and sawing every piece of concrete. The NICU, OR, and burn unit patients are on the other side of the wall making it impossible to chip out any concrete because noise and vibrations are a top concern.

When excavation began on its 2nd floor below grade many of the footings and foundation walls were different than expected. This caused us to re-evaluate our footings and construction methods. We also had to do much more concrete demolition and calculate just how much of the existing concrete we could shave off. It’s critical that our walls are exactly as designed to maintain the already extremely tight spaces in the operation rooms and patient rooms above.

One of the more challenging aspects of the job was designing the micropyles. Typically, obtaining a geotechnical report would happen during design, however, because we couldn’t get the drilling equipment in without a crane we waited until demolition was complete and before excavation. It was a race to design the micropyles with code approval before the excavation team finished. The design had to support an eccentrically loaded footing and be constructible on a very confined site with multiple elevation changes. In the end, we had over 200 micropyles on a 1300 sqft. site. Everyone came together and collaborated to accomplish this.

There are more challenges ahead with fire protection, expansion joints, and preparing for the operating equipment. Now that the project has come up out of the ground by a floor we feel like the biggest challenges are behind us.

– written by Barton Done

Grand Opening: The Lodge

 

This month, Rocky Mountain Care held the Grand Opening for their newest facility, The Lodge, located in Heber City, Utah. This gorgeous facility integrates a host of amenities for their residents and their families, including alfresco dining areas, a gorgeous community theatre room, therapeutic golf greens, therapy spa, and hair salon. Those who live at The Lodge enjoy a wide array of activities promoting social relationships and experience next-level care.

We could not be more grateful or more proud to work with Rocky Mountain Care. Their dedication to bringing the very best to their patients in all their facilities and consistently providing excellent and individualized care, makes their motto “Simply the best care” very well suited.

Mountain View Care Center Update

Rocky Mountain Care Heber is coming to life!  The progress at Rocky Mountain Care has come a long way in the last couple of months.    Exterior and Interior finishes are adding character and personality to the architecture.  Siding, stucco, and masonry are all underway on the exterior, adding color and depth to the Heber Landscape.  On the interior gypsum board, t&g ceiling, and masonry details are making this building feel more and more like home!  We are excited about the progress!  We couldn’t make this progress happen so smoothly without the astounding team efforts made by TSA, Ascent Construction, and Rocky Mountain Care!

 

Project Commission: University of Utah Huntsman Arena Scoreboard Replacement

We’re very excited to partner with North Ridge and ANC to replace the University of Utah Huntsman Arena Scoreboard. As an office generously staffed with Utah alumni, we always enjoy a chance to give back and nurture a lifelong relationship with the University.

Our contributing team members include Tracy Stocking (code review) and John Meredith (planning and drawing support).

The project scope will include dismantling the existing scoreboard, replacement of the center-hung digital screens with a new modular assembly with multiple 1080p HD screens, and replacing other LED and projection screens with HD LED screens.

Rocky Mountain Care – Heber City Ground Breaking

This past week we celebrated the groundbreaking for the RMC Heber Skilled Nursing Facility. The groundbreaking was attended by members of RMC ownership, the Heber City mayor, construction team, design team, and residents of the existing RMC Heber facility.

Located in Heber, Utah, the new facility will be nestled inside native, woodsy landscaping complete with a dry creek and tall trees. Accommodating up to 110 patients in both private and semi-private rooms, RMC Heber provides a large selection of day-to-day amenities and activities including a beauty parlor, occupational and physical therapy services, private and public dining, lush courtyards, and resident neighborhood wings.

The entrance is across a bridge and into a garden area before you reach the main lobby which is wrapped by tall curtain glass windows. From the lobby is direct access to the “main street” area where the activity and life of the facility will flow. Down main street you feel like you are walking along store fronts with hanging lanterns, planters, and a large skylight above. From here you have access to every amenity. At the far ends of the resident wings there are gathering areas around fire places which are open to the inside and outside in the courtyards for all the residents to enjoy.

Figure 1: Construction has commenced!

Estimated completion and grand opening is fall of 2018.

Here is a link to a virtual tour video of the new facility.

tsa architects rending of exterior new office

2017 Newsletter: Edition Two

Project Updates

TSA Architects is assisting University Hospital with the remodel of two catheterization labs that will keep the state’s flagship academic hospital at the forefront of Cath Lab imaging technology. Cath Lab 2 will house a new Philips Allura FD20 Catalyst imaging system. Cath Lab 3 will be enlarged to provide more procedure space, and see a replacement of the Siemens equipment with a new Artis Q imaging system. Anesthesia, light and equipment ceiling booms by Skytron are being added to improve safety and efficiency by bringing power, data and medical gas lines overhead directly to the patient. Both lab’s control rooms will be remodeled to support the new equipment and staff work process. The entire Lab 2 & 3 suite will be updated to the current hospital standard for interior finishes. Construction work will begin in early June and should be complete by November.

Design Team

Project Manager and Architect: Doug Banks
Interior Design and Project Support: Stephanie Kwok
Project Support: Frederick Berte


VAMC North Campus Transformation

We’re excited to announce that construction has commenced on Phase 2 of the North Campus Transformation at Salt Lake City’s George C Whalen VA Medical Center.  This Rehabilitation & Prosthetics Expansion-visible along Foothill Blvd-will provide significant Inpatient Physical & Occupational Therapy and Exam areas, as well as easily-accessible Outpatient Prosthetic & Mobility Support to improve care for our wounded veterans.  It will also create a new, two-level East entry to the Hospital that embraces views to the Wasatch Mountains.  We are thrilled to team with the VA Healthcare System in designing facilities that better enable their mission.

Design Team

PIC:  Tracy Stocking
Design Principal:  Nathan Murray
Interior Designer:  Stephanie Kwok
Project Coordinator:  Blake Fredrickson
Project Manager:  Doug Banks


BUSINESS SERVICES BUILDING PLAZA REMODEL

The Business Services Building is a 5-story office building with 2 levels of underground parking. This parking garage has a larger footprint than the building and approximately 27,000 sf of plaza covers the balance of the garage. The plaza consists of a suspended structural slab with topping slab and various planters and landscaping and is terraced into 2 levels. Our exploratory observations revealed that there is no waterproofing system between the plaza deck and the structural slab. This appears to be the cause of most of the leakage.

The primary driver is to remove the existing plaza deck, install a rubberized asphalt waterproofing system and a new plaza deck with landscape features. The financial driver of the project provided an exciting opportunity to improve the aesthetics and functionality of the plaza. Creative design charrettes were held with the representatives of all the departments housed in the building, over two months, culminating in an optimized plaza redesign. The project includes replacement and upgrading the plaza landscape, creating a campus shuttle stop at to serve hospital patients and other building staff and visitors, and creating various shaded gathering and multi-function outdoor spaces for the 500 building occupants, including natural and artificial shade, convenience power, a gas grill, and myriad seating and gathering configurations.

Architectural renovation of the plaza for the purpose of making it more engaging, functional and inviting will include the hardscape portions of the plaza such as the plaza deck, retaining and planter walls, stairs, and railings. Landscape improvements to the plaza will support the architectural goals stated above with new planting beds, trees, and lighting. The landscaping at the perimeter of the plaza will replace the existing sod with new xeriscape plantings. All new landscaping will be drought tolerant, and upgrade the scheme to Salt Lake City and University standards.

Design Team

PIC:  Tracy Stocking
PIC: Tracy Stocking
Design Principal: Nathan Murray
Project Manager: John Meredith
Project Designer: Frederik Berte
Landscape Architect: Richard Gilbert (ArcSitio Design)



Staff News

TSA Architects is excited to announce the promotion of Douglas Banks, AIA to Principal Architect, and Board Member. A recognized expert in healthcare architecture, over his 25-year career, he has assisted many healthcare facilities with the design of highly complex spaces such as operating suites, imaging centers, and cardiac Cath labs. Doug earned his Master of Architecture degree from the University of Utah and has spent his career providing architectural healthcare services throughout the intermountain region. His natural ability to coordinate the complexities of leading edge medical technology in critical care settings has earned the trust and respect of major health care systems. He brings with him a collaborative philosophy and focuses on sophisticated healthcare clients to improve their mission-driven operations.
Doug’s clients include: University of Utah Health, Intermountain Healthcare, HCA/MountainStar, Iasis Healthcare, VA Medical Center and many other healthcare systems in the western United States. Recent notable projects include Hybrid Operating Rooms for Intermountain Healthcare at McKay Dee Hospital and Intermountain Medical Center.

Doug Banks can be reached at: dbanks@tsa-usa.com & (801) 463-7108


We are pleased to announce the addition of Rebecca Weidler to our team as our new Healthcare Planner. Rebecca is a recent transplant from Philadelphia with a decade of experience in architecture for health. Originally from Long Island, New York, she obtained her Master of Architecture from the Pratt Institute and her Bachelor of Arts from Southern Virginia University. She will be overseeing planning for the new Brigham City Hospital OR Expansion, and joining the University Hospital Infill Project team. Outside of work, she enjoys all kinds of creative pursuits including fashion design, drawing, sewing, and experimenting in the kitchen.


NEW OFFICE UPDATE

A sneak-peek of the inner workings of our new office! We’re looking forward to increased work space, easily-accessible sample storage, and expanded conference areas – as well as easy parking.